Breaking the record again!High efficiency and high quality won the praise of the ship owner

01.jpg

Shanghai Bluesoul environmental technology Co., Ltd. (Shanghai Bluesoul, thereafter) Completed, in 18 days, the retrofitting task for Stena Impero, an EPC turnkey project to install scrubber.

 On December 28, 2019 and January 7, 2020, Shanghai Bluesoul completed respectively the retrofitting tasks for Stena Impression and Stena Impero to install scrubber on Qinzhou Sandun Base of Shanghai Bluesoul and officially delivered the two vessels to the owner. The high efficiency and high quality of the retrofitting, completed within 18 days for each vessel, have won the praise of the ship owner.

02.jpg

 Stena Impression and Stena Impero have a load capacity of 50000 tons with length of 183 meters and width of 32.26 meters.  The main works of the retrofitting project include the installation of the scrubber on the original chimney exhaust system, complying with the latest environmental protection emission standards, the production and installation of a new sea chest, and the installation of a new hybrid reserved desulfurization system and monitoring equipment as well as its pipeline and electrical system.  There are two tough issues: 1. the total work volume is huge, and 2. the ship owner is the Stena bulk ship management company in Sweden, which is famous for its highest and strictest safety and quality standards in the industry.


03.jpg

After signing agreement, the management team of Shanghai Bluesoul carefully organized the operation engineers to take care of the project, and made the production plan and preparation. To meet the requirement of the ship owner for high quality and high efficiency, the desulfurization system possesses the characteristics of small size, high efficiency, low energy consumption and low back pressure.  In the manufacturing and installation processes, the integration degree of prefabricated desulfurization sections and desulfurization system pipes had been improved, so that the integrated equipment can be directly hoisted up on the ship after the ship entering the shipyard; and labor force and docking time had been arranged based on the project needs, to ensure the smooth progress of the project and optimize the construction process, so that all kinds of work start at the same time without cross operation.  In this way, the time period of the retrofitting had been greatly shortened with safety and quality.

04.jpg

Stena Bulk in Sweden praised Shanghai Bluesoul for its completing the retrofitting (EPC) project to install scrubber on Stena vessel in only 18 days.  Mr. Yao Hao, Chairman of Shanghai Bluesoul, said that this achievement had been achieved under the overall planning and careful arrangement of Bluesoul management team and overcoming various difficulties. The breaking record of time period not only proves the strength of Shanghai Bluesoul, also unveils the brand of Bluesoul.  The 18 days of retrofitting to install scrubber with high efficiency and quality has also set a new record of retrofitting for the same type of ships and a benchmark in the industry.